Track access charge
What this is
What the operator pays each country's infrastructure manager for the right to run over its track. For a cross-border night train this is usually the largest infrastructure cost and the most variable.
What the operator pays each country's infrastructure company for using the track.
The formula
| Symbol | Meaning | Unit | Where it comes from | |
|---|---|---|---|---|
| Input | d_c | Distance driven in this country on this segment | km | computed upstream |
| Input | nu_c | Share of the run in this country priced at the night rate | – | tac_night_share |
| Input | b_day,c | The country's day rate per train-kilometre | €/train-km | track_tac_b_day |
| Input | b_night,c | The country's night rate per train-kilometre | €/train-km | track_tac_b_night |
| Input | gamma_c | The country's rate per tonne of train weight and kilometre | €/(t·km) | track_tac_gamma |
| Input | m_gross | Weight of the whole train — coaches plus locomotives | t | loco_type_weight_t |
| Input | sigma_c | The country's rate per place and kilometre | €/(place·km) | track_tac_seat_km |
| Input | P | Places the train offers | places | computed upstream |
| Input | phi_c | The country's flat administrative add-on per train-kilometre | €/train-km | track_tac_fixed_per_train_km |
| Input | kappa_c | The country's congestion surcharge per train-kilometre | €/train-km | track_tac_congestion_surcharge_eur_km |
| Input | pi_c | Share of the run in this country falling in rush hour | – | tac_peak_share |
| Input | mu_c | Factor the day rate is multiplied by over the rush-hour share of the run (1 outside it) | factor | track_tac_peak_multiplier |
| Input | h_country(stop) | Fee for making one stop, at that stop's own country rate. A trip's first segment pays for both of its ends, since no other segment owns the starting station | €/stop | track_tac_per_stop |
| Input | rho_c | Share of the ticket revenue earned in this country that the infrastructure manager takes | fraction | track_tac_revenue_share |
| Input | R_seg,c | Ticket revenue attributable to this segment in this country, per train run | €/trip | computed upstream |
| Input | F_x | Charge for crossing a separately billed link, per train | €/traverse | passage_fixed_eur |
| Input | f_x | Charge for crossing a separately billed link, per passenger | €/passenger | passage_per_passenger_eur |
| Input | n_seg | Passengers aboard on this segment, per train run | passengers | computed upstream |
| Result | C_TAC | Annual track access charges | €/year | — |
Feeds into: infrastructure_total_eur
Found a mistake?
This documentation describes a model that is still being built, and some of it will be wrong. If a number looks off, a source is missing, or an explanation does not hold up, tell us — it reaches the working group with the page you were reading.